RERC Releases Discom Performance Standards 2021

Yellow HazeEnergy transition insights

On 19th February 2021, the Rajasthan Electricity Regulatory Commission (RERC) issued Regulations for Discom Performance Standards 2021. As per these regulations the distribution companies will have pay compensation to the consumers for failure in ensuring services.

These RERC (Standards of Performance for Distribution Licensees) Regulations, 2021 shall be applicable to all the Distribution Licensees including Deemed Licensees/ Franchisees and all of its consumers in the state of Rajasthan.

Objectives of Regulations for Discom Performance Standards 2021

These regulation have been released with an objective to lay down the standards to maintain distribution system parameters within the permissible limits. These standards shall serve as benchmark for Licensees/franchisee for providing an efficient, reliable, coordinated and economical system of electricity distribution. It is the right of consumer to have minimum standards of service for supply of electricity from the distribution licensee in accordance with the provisions made in these Regulations.

The objectives of these Regulations are:

  • (a) to lay down standards of performance;
  • (b) to measure the actual performance of licensee/franchisee as against the benchmarks standards of performance.
  • (c) to ensure quality and suitability of distribution network performance.
  • (d) to enable the consumers to design their systems and equipment to suit the electrical environment that they operate in;
  • (e) to improve service delivery to the consumers.
    (f) to develop transparent mechanism for ensuring fair compensation to the consumers in case the Licensee fails to achieve guaranteed benchmark standard of performance as described in these Regulations.

Highlights of Regulations for Discom Performance Standards 2021 :

  • Overhead line /overhead cable break down has to be rectified within four hours in cities, while six hours in urban areas and 10 hours in rural areas.
  • Distribution transformer failure has to be rectified within 8 hours in city and urban areas, while it is 24 hours in rural areas.
  • Power transformer failure has to be put on track within 48 hours in city, urban and rural areas.
  • In case of failure of a licencee/franchisee to meet the Guaranteed Standards of Performance and completion within actual time as specified in these regulations as well as Supply Code Regulations, compensation should be payable to the consumer by the licensee/franchisee.
  • There shall be an IT enabled centralized customer care centre at licensee/franchisee headquarter.
  • The complaint number shall be communicated to the consumer by the Licensee within 30 minutes of receiving the complaint

References:

RERC – Discom Performance Standards 2021 – Download PDF

Keep reading

Related insights

News

India’s 500 GW Non-Fossil Capacity Push: What The Bharat Renewable Energy Summit Says It Will Take

India 500 GW non-fossil capacity: the 2030 target needs about USD 220 billion, and a new 500 GW goal follows. What the BRE Summit says it will take.

11 min read

News

India Grid-Scale Energy Storage VGF Scheme: Rs 14,500 Crore Backs 92 GWh Of BESS, Pumped Storage And Domestic Cells

India's grid-scale energy storage VGF scheme puts Rs 14,500 crore behind 92 GWh of pumped hydro and batteries: what it funds, who bids, what is still open.

7 min read

News

E85 And E100 Flex Fuel Vehicles In India: What The CMVR Amendment Changes

India now certifies E85 and E100 flex fuel vehicles under amended CMVR rules. What changes for carmakers, owners and the ethanol roadmap beyond E20.

6 min read

Scroll to Top